Project Scope

 

C-NS High School

Entire Building: Remove existing interior door hardware and replace with District standard, BEST lock system to include intruder security hardware.

Benefit: Replace non ADA complaint door hardware with code complaint hardware. Upgraded security features that allow any room to be locked from the inside with any key, but only allow exterior locking/unlocking capability for those authorized access to the space.

Michael J. Bragman Stadium

  • Replacement of turf field.
  • Resurfacing of the running track.
  • Repair of turf field drainage issues.

Benefit: Turf Field Replacement. The turf field was installed in the Fall of 1999, as part of Phase 1 of the C-NS High School/Athletic Stadium Capital Project.

The original life expectancy of the field was 8 years to include the warranty, the field consisted of Astroturf 2000, installed over an elastic layer (E layer) with a 3/8" polyurethane shock pad.

Concerns with this type of field are typically ultraviolet degradation of the carpet fiber and a decrease in resilience (becomes harder) as it ages.

Maintenance costs – although the District has done an exceptional job of maintaining and prolonging the life expectancy of the field through constant monitoring and maintenance. The yearly cost for the upkeep of the field has gone from $12,000 in the first 6 years to over $50,000 this past fiscal year.

The photos below show issues with the field's current turf:

 

 

 

 

 

The next photos show issues with drainage and the track:

 

 

 

 

 

 

The following photo shows the project repair locations: